千亿|国际手机|官网

  •  

    Published here July 2017

    Introduction | The Challenge
    Justification for Different Groupings: Project Management Hierarchy | Industry/Product Sectors
    Internet Research | Taming the Long List of Industry Sectors
    Significant Difference in Types of Output | Putting "Work" and "Product" Together
    Comments Regarding Appendix A | Summary of Our Deliberations

    Putting "Work" and "Product" Together

    As a side note, in many of the more recent definitions added to our Glossary, the term "Technical" refers to the work of creating the project's product. This is in contrast to referring to the numeric type topics of project management such as managing cost, or developing a network schedule. Moreover, this technical (product development) work is typically conducted in "Stages", while the management of the Project as a whole is typically separated into "Phases".

    For example, in PRINCE2 there are two types of time divisions. A project is divided into "phases" to define management decision points — PRINCE2 calls these "Management Phases". The second type is the "Technical Stages" that are groupings of selected technical techniques used in the development of the product.

    These two classes of time intervals do not necessarily overlap but rather, in normal planning, the Phases of Project Management encompass the Stages of Technical Product Development.

    Now, if we put Work and Product together as a 2x2 matrix we arrive at a basic Project Classification as shown in Figure 2:[8]

    Type of Work in the Project

    Intellect

    3. Example: Development of an all-new electric car

    4. Example: Development of a new theory

    Craft

    1. Example: Detailing and construction of a building

    2. Example: Updating a procedures manual

     

    Tangible

    Intangible

     

     

    Type of Product from the Project

    Figure 2: Basic 2x2 Project Classification based on primary products

    To arrive at practical terms and their respective definitions for the four types shown in the chart, we researched the listings of industry sectors presented earlier. They are listed as columns A through H as shown in Appendix A, Figures A1 and A2: Tables of Industry Sectors According to Different Sources".

    Significant Difference in Types of Output  Significant Difference in Types of Output

    8. Ibid maxwideman.com/papers/differentiation/matrix.htm
     
    Home | Issacons | PM Glossary | Papers & Books | Max's Musings
    Guest Articles | Contact Info | Search My Site | Site Map | Top of Page
  • 中博的彩首页

    彩名堂计划app登录

    即送彩金的娱乐平台

    大赢家足球即时比分球探网

    银河国际澳门

    梦之城注册登录

    亚洲通网站

    大赢家网即时比分

    鸿丰在线/登录彩